A fire rated cable tray often appears in the specification as a single line: route to be E90. For the person planning the installation, a whole chain sits behind that line. The rating belongs to a system that was tested as a whole in a furnace: cable, containment, supports and fixings together. Swap one component and the rating is gone. Below: what E30, E60 and E90 mean, how they differ from the FE180 cable marking, how UK standards fit in, what changes in the supports and how to check the components.
What does circuit integrity mean for a cable support system?
Circuit integrity means an electrical installation keeps working for a set time during a fire. The class gives the number of minutes:
| Class | Duration | Test |
|---|---|---|
| E30 | 30 minutes | DIN 4102-12 |
| E60 | 60 minutes | DIN 4102-12 |
| E90 | 90 minutes | DIN 4102-12 |
Classes to DIN 4102-12 [1]. Manufacturers describe E90 as a 90-minute test reaching about 1,000 °C [6].
In the test the complete system hangs in a furnace: cable, tray or ladder, couplers, supports and the fixing into the soffit. It has to keep conducting for the full duration without short circuit or interruption. If the supports fail, the cable drops and the circuit is lost, which is why the supports matter as much as the cable.
What is the difference between FE180 and E90?
Fire-resistant cables are often marked FE180/E90. The marking has two parts:
- FE180 refers to the cable alone. Its insulation survives 180 minutes in a fire test to IEC 60331 [2]. Small cables can also be tested to BS EN 50200, which gives PH classes [3].
- E90 refers to the system: this cable, on this support system, with these fixings, keeps circuit integrity for 90 minutes to DIN 4102-12 [1].
E90 only comes from the tested combination in the report. An FE180 cable on an arbitrary tray is not enough.
How do UK standards fit in?
On UK projects, fire performance of cable installations is usually specified through British Standards:
- BS 8519 covers the selection and installation of fire-resistant power and control cable systems for life safety and fire-fighting applications [4].
- BS 5839-1 covers fire detection and alarm systems, including their cabling [5].
- BS 7671 regulation 521.10.202 requires wiring systems to be supported so they will not collapse prematurely in a fire [7]. That applies to every installation, so use metal supports and fixings throughout.
E30 to E90 to DIN 4102-12 appear on many manufacturers’ data sheets and on European projects. Where both appear in a specification, check with the designer which one governs.
What changes in the supports?
| Component | Standard route | Fire rated route |
|---|---|---|
| Tray and fittings | Any suitable system | Only components from the test report |
| Couplers | Click-fit or quick couplers | Often a reinforced coupler |
| Support centres | 1.5 m tray, 3 m ladder (rule of thumb) | As per the test report, usually shorter |
| Cable load per metre | Within the safe working load | Limited to the value in the report |
| Drop rods | Sized for the load | Sized for the load at fire temperature, per the report |
| Anchors | For substrate and load | Fire-approved for the substrate |
| Plastic parts | Acceptable | None in the load path |
Practical overview, indicative. The system’s test report governs; check with the manufacturer.
Steel loses much of its strength at high temperature. Tested systems therefore work with lower loads per rod and per metre of tray than a standard route, and those values come from the test report. Never apply the standard load table to a fire rated route. For standard routes, see cable tray supports.
How do you identify suitable components?
Many manufacturers state per component, on the product page, whether it is suitable for circuit integrity. Some examples from one wire basket range [6]:
| Component | Suitable for circuit integrity |
|---|---|
| Wire basket 100×600 mm, hot-dip galvanised | Yes |
| Reinforced coupler (E90 to DIN 4102-12) | Yes |
| Fixing clamp M6×20, hot-dip galvanised | Yes |
| Click-fit coupler plate, electro-galvanised | No |
| Centre hanger M6 | No |
Manufacturer data [6], accessed 19 November 2026.
Two lessons from that list. First, suitability varies per component, even within one run: the basket can qualify while its click-fit coupler does not. Second, product pages are not always consistent. For a support profile in the same range, the description mentions E90 to DIN 4102-12 while the specification lists circuit integrity as no [6]. When in doubt, ask for the test report.
What mistakes come up most on fire rated routes?
- A standard bracket between tested parts. One bracket, clamp or coupler that is not in the report, and the rating no longer applies to the route.
- Anchors without fire approval. The anchor in the concrete must itself be fire tested. A standard anchor can bring the whole support down.
- Cables added later. Standard cables laid in after handover add load and fall outside the report.
- Support centres too wide. The route is hung at standard centres while the report requires shorter ones.
- Plastic ties as the only fixing. Plastic fails in a fire. Use metal cleats or fixings from the tested system.
- No marking. Without a marking on the route, a fitter later has no way of knowing special requirements apply.
What should the bill of materials record?
A fire rated route must be verifiable at handover. Include:
- the class (E30, E60 or E90) per route;
- the system and test report reference;
- every component in the version listed in the report, anchors included;
- the support centres and maximum cable load from the report;
- the cables with their markings, so the combination matches;
- a marking on the route so nobody later hangs a standard cable or bracket from it (rule of thumb).
In the configurator, the first step is the environment. If you indicate that circuit integrity in a fire is required, the configurator shows a notice that the components must be checked with the manufacturer against the test report. The bill of materials and drawing support that check. The rating itself only ever comes from the tested system.
Where do these figures come from?
- DIN 4102-12, Fire behaviour of building materials and building components. Part 12: Circuit integrity maintenance of electric cable systems.
- IEC 60331, Tests for electric cables under fire conditions. Circuit integrity.
- BS EN 50200, Method of test for resistance to fire of unprotected small cables for use in emergency circuits.
- BS 8519, Selection and installation of fire-resistant power and control cable systems for life safety and fire-fighting applications. Code of practice.
- BS 5839-1, Fire detection and fire alarm systems for buildings. Code of practice for design, installation, commissioning and maintenance of systems in non-domestic premises.
- Eurostrut, wire basket and accessory product pages, specification field for circuit integrity and E90 description (90 minutes, 1,000 °C) to DIN 4102-12. Accessed 19 November 2026. https://eurostrut.com/kabeldraagsystemen/pemsa-rejiband-draadgoten/ · https://eurostrut.com/rejiband-versterkte-koppeling-tv/64030061
- BS 7671, Requirements for Electrical Installations (IET Wiring Regulations), regulation 521.10.202.
Frequently asked questions
What does E90 mean for cable tray?
E90 means the tested cable system, with cable, containment, supports and fixings, keeps working for 90 minutes in a fire. The test is set out in DIN 4102-12. The rating only applies to the combination exactly as tested.
What is the difference between FE180 and E90?
FE180 refers to the cable alone: its insulation survives 180 minutes in a fire test to IEC 60331. E90 refers to the whole system of cable plus support system, tested to DIN 4102-12. A cable marked FE180 does not on its own give circuit integrity.
Which UK standards cover fire resistant cable installations?
BS 8519 covers fire-resistant power and control cable systems for life safety and fire-fighting applications, and BS 5839-1 covers fire alarm cabling. BS 7671 regulation 521.10.202 requires wiring systems to be supported against premature collapse in a fire.
Can standard cable tray be used for circuit integrity?
Only if that tray, with the chosen cable and supports, appears in a test report. Product pages often state per component whether it is suitable for circuit integrity. If one component is missing from the report, the rating does not apply to your route.