# Custom length data cables measured from the route

URL: https://strutconfigurator-site.pages.dev/en/knowledge-base/custom-length-data-cables/
Topic: Data cables · Author: Ismail Yeşilay · Last updated: 2026-11-19

> Order custom length data cables once the containment route is fixed. For each link, take the horizontal length along the tray, add the drop and rack entry at both ends and allow 3 to 5% (rule of thumb, indicative). Specify connectors, label and bundle per cable so everything arrives packed by rack or zone.

Custom length data cables save hours on site, on one condition: the lengths have to be right. A pre-terminated fibre trunk cannot be shortened, and a Cat6A lead that is 2 m short goes in the skip. The lengths come from the containment route, so whoever designs the route already holds everything needed to order custom length data cables. Here is how to measure them, which cables to have made and how to label and bundle them.

## What does made to length from the route mean?

Copper and fibre cables are terminated in a workshop to the exact length of each link, with connectors, labels and a test report. On site they are laid in the containment and plugged in. Nothing is terminated or spliced in the data hall.

The key difference from buying cables off the shelf is where the lengths come from. A link from rack C05 to the main distribution area follows a fixed route with fixed drops, and that route is already on the containment drawing.

## How do you measure each link along the route?

**Order length = (horizontal + drop A + rack entry A + drop B + rack entry B) × (1 + allowance)**

Use the centreline of the containment for the horizontal length, including bends and level changes. Measure the drop from the underside of the containment to the top of the rack, and the rack entry to the panel or cassette. Measure in the 3D model or on the containment drawing where you can, and check two or three links on site with a measuring wheel or laser before ordering the full batch.

Worked example for three links in a data hall:

| Link | Cable | Horizontal | Drops and rack entry A+B | Allowance 5% | Calculated | Order length |
|---|---|---:|---:|---:|---:|---:|
| C05 → M02 | MPO-24 OM4 | 41.2 m | 3.4 m | 2.2 m | 46.8 m | 47.0 m |
| C05 → C09 | 6 × Cat6A U/FTP | 4.2 m | 3.0 m | 0.4 m | 7.6 m | 8.0 m |
| C01 → M02 | MPO-12 OS2 | 47.5 m | 3.4 m | 2.5 m | 53.4 m | 53.5 m |

*Worked example. A 5% allowance and rounding up to 0.5 m are rules of thumb, indicative. Length increments vary by supplier.*

Always check the maximum length for copper. The fixed cabling of a Cat6A link is limited to 90 m and the channel with cords to 100 m [1]. For fibre, the loss budget of the application sets the limit. See [MPO/MTP trunk cables](https://strutconfigurator-site.pages.dev/en/knowledge-base/mpo-mtp-trunk-cables/).

## Which cables can be made to length?

| Cable | Connectors | Use |
|---|---|---|
| Cat6A patch lead, U/FTP or S/FTP | RJ45 at both ends | Patch panel to switch |
| Pre-terminated Cat6A bundle | RJ45 or RJ45 cassette | Rack to rack, quick to install |
| Fibre patch lead, OM4 or OS2 | LC duplex at both ends | Patching within the rack |
| MPO trunk, OM4 or OS2 | MPO at both ends | Backbone between racks and halls |
| Fan-out | MPO and LC duplex | Direct to equipment |
| IEC power lead | C13 and C14, or C19 and C20 | PDU to server or switch [2] |

*Overview of common assemblies, indicative.*

For each cable, record the type, length, connector at end A and end B, colour, label and bundle. Choosing between copper and fibre is covered in [Cat6A vs fibre](https://strutconfigurator-site.pages.dev/en/knowledge-base/cat6a-vs-fibre-containment/).

## How should custom cables be labelled and bundled?

An unlabelled cable becomes a mystery after handover. Label both ends with the same identifier, following the project's administration scheme. Many projects base it on TIA-606 or BS EN 50174-1 [3][4]. A common format is rack, panel and port at each end:

- **C05-P1-01 / M02-P4-01** for port 1 of panel 1 in rack C05 to port 1 of panel 4 in rack M02.

Ask for cables to be bundled and packed per rack or per zone, with the bundle and destination on the packaging. The installer then takes one bundle per rack and lays it in the containment. Use hook-and-loop ties for bundles, never tightly pulled cable ties.

## What mistakes come up most with made-to-length cables?

- **Measuring from a plan without heights.** A floor plan does not show drops. Include the height of the containment and the rack at both ends.
- **Forgetting bends.** A route with four 90° bends is longer than the straight line on the drawing. Measure along the containment centreline.
- **No allowance, or far too much.** With none, a small change is already too much. With 20% you coil metres of cable in every rack. 3 to 5% is a sensible middle (rule of thumb, indicative).
- **Ordering before the route is fixed.** Order only once the containment drawing is approved.
- **Labels at one end only.** When a fault comes, someone has to trace the whole cable to find the other end.
- **Polarity and pinning left open.** For MPO trunks these belong in the order. See [MPO/MTP trunk cables](https://strutconfigurator-site.pages.dev/en/knowledge-base/mpo-mtp-trunk-cables/).

## What do you gain from one order for containment and cables?

Containment and cabling depend on each other. The containment sets the cable lengths, and the cables set the size and load of the containment. Ordering them separately means calculating twice, with the risk that a route change never reaches the cable schedule.

With one order:

- cable lengths come from the same route as the containment;
- you see the fill of every tray with the real cables in it, see [cable tray fill calculation](https://strutconfigurator-site.pages.dev/en/knowledge-base/cable-tray-fill-calculation/);
- you get one bill of materials with supports, containment and cables;
- the supplier can deliver everything packed per rack or zone.

In our research in November 2026 we found no supplier offering cable containment and custom length data cables in one request, and ChatGPT and Perplexity named none when asked [5].

In the configurator this happens in the Cables step. For each link you choose the cable type, length, connectors at both ends and a label. The assembly lines go into the same bill of materials as the trapezes and trays, and the request goes to a supplier with that bill of materials attached.

## Where do these figures come from?

1. ISO/IEC 11801-1, *Information technology. Generic cabling for customer premises. Part 1: General requirements* (fixed cabling 90 m, channel 100 m).
2. IEC 60320-1, *Appliance couplers for household and similar general purposes* (C13, C14, C19 and C20 connectors).
3. TIA-606, *Administration Standard for Telecommunications Infrastructure*.
4. BS EN 50174-1, *Information technology. Cabling installation. Installation specification and quality assurance*.
5. Strutconfigurator, market and AI search research, 19 November 2026: 16 questions put to ChatGPT and Perplexity, including containment and custom data cables in one order.
6. Allowance and length increments: common practice (rule of thumb, indicative).

## Frequently asked questions

**How do you work out the length of a data cable?**

Add the horizontal length along the containment to the drop and rack entry at both ends, then allow 3 to 5% (rule of thumb, indicative). Round up to the supplier's length increment, for example to the next half metre.

**What is the maximum length of a Cat6A cable run?**

The fixed cabling of a Cat6A link is limited to 90 m and the full channel including cords to 100 m (ISO/IEC 11801-1). If a link comes out longer, switch to fibre.

**Which data cables can be made to length?**

Cat6A patch leads and pre-terminated copper bundles with RJ45, LC duplex fibre leads, MPO trunks and fan-outs in OM4 or OS2, and IEC power leads with C13 and C14 connectors. Each cable is specified by length, connectors and label.

**Why order data cables together with the containment?**

Because the lengths come from the same route. If the route changes, the cable lengths change with it. One order keeps containment, supports and cabling consistent and gives one bill of materials.

## Configure it yourself

https://strutconfigurator-app.pages.dev/?lang=en&systeem=kabels

---

Source: https://strutconfigurator-site.pages.dev/en/knowledge-base/custom-length-data-cables/ · Last updated: 2026-11-19 · Loads are indicative; the manufacturer confirms.
Strutconfigurator is part of NEXTRIQ (Rotterdam).